Are you looking for read ebook online? Search for your book and save it on your Kindle device, PC, phones or tablets. Download Final Deactivation Report On The Tritium Target Facility Building 7025 At Oak Ridge National Laboratory Oak Ridge Tennessee PDF full book. Access full book title Final Deactivation Report On The Tritium Target Facility Building 7025 At Oak Ridge National Laboratory Oak Ridge Tennessee.

Final Deactivation Report on the Tritium Target Facility, Building 7025, at Oak Ridge National Laboratory, Oak Ridge, Tennessee

Final Deactivation Report on the Tritium Target Facility, Building 7025, at Oak Ridge National Laboratory, Oak Ridge, Tennessee
Author:
Publisher:
Total Pages: 102
Release: 1997
Genre:
ISBN:

Download Final Deactivation Report on the Tritium Target Facility, Building 7025, at Oak Ridge National Laboratory, Oak Ridge, Tennessee Book in PDF, ePub and Kindle

This report includes a history and profile of Bldg. 7025 before and after completion of deactivation. It also discusses turnover items, such as the Postdeactivation Surveillance & Maintenance Plan, remaining hazardous materials, radiological controls, Safeguards and Security, quality assurance, facility operations, and supporting documentation in the EM-60 Turnover package. Other than minimal S & M activities, the building will be unoccupied and the exterior doors locked (access only for the required S & M).


Final Deactivation Project Report on the Integrated Process Demonstration Facility, Building 7602 Oak Ridge National Laboratory, Oak Ridge, Tennessee

Final Deactivation Project Report on the Integrated Process Demonstration Facility, Building 7602 Oak Ridge National Laboratory, Oak Ridge, Tennessee
Author:
Publisher:
Total Pages: 104
Release: 1997
Genre:
ISBN:

Download Final Deactivation Project Report on the Integrated Process Demonstration Facility, Building 7602 Oak Ridge National Laboratory, Oak Ridge, Tennessee Book in PDF, ePub and Kindle

The purpose of this report is to document the condition of the Integrated Process Demonstration Facility (Building 7602) at Oak Ridge National Laboratory (ORNL) after completion of deactivation activities by the High Ranking Facilities Deactivation Project (HRFDP). This report identifies the activities conducted to place the facility in a safe and environmentally sound condition prior to transfer to the U.S. Department of Energy (DOE) Environmental Restoration EM-40 Program. This report provides a history and description of the facility prior to commencing deactivation activities and documents the condition of the building after completion of all deactivation activities. Turnover items, such as the Post-Deactivation Surveillance and Maintenance (S & M) Plan, remaining hazardous and radioactive materials inventory, radiological controls, Safeguards and Security, and supporting documentation provided in the Office of Nuclear Material and Facility Stabilization Program (EM-60) Turnover package are discussed.


Final Deactivation Project Report on the High Radiation Level Analytical Facility, Building 3019B at Oak Ridge National Laboratory, Oak Ridge, Tennessee

Final Deactivation Project Report on the High Radiation Level Analytical Facility, Building 3019B at Oak Ridge National Laboratory, Oak Ridge, Tennessee
Author:
Publisher:
Total Pages: 82
Release: 1997
Genre:
ISBN:

Download Final Deactivation Project Report on the High Radiation Level Analytical Facility, Building 3019B at Oak Ridge National Laboratory, Oak Ridge, Tennessee Book in PDF, ePub and Kindle

The purpose of this report is to document the condition of the High Radiation Level Analytical Facility (Building 3019B) at Oak Ridge National Laboratory (ORNL) after completion of deactivation activities. This report identifies the activities conducted to place the facility in a safe and environmentally sound condition prior to transfer to the Environmental Restoration EM-40 Program. This document provides a history and description of the facility prior to the commencement of deactivation activities and documents the condition of the building after completion of all deactivation activities. Turnover items, such as the Post-Deactivation Surveillance and Maintenance (S & M) Plan, remaining hazardous materials inventory, radiological controls, safeguards and security, quality assurance, facility operations, and supporting documentation provided in the Nuclear Material and Facility Stabilization (EM-60) Turnover package are discussed. Building 3019B will require access to perform required S & M activities to maintain the building safety envelope. Building 3019B was stabilized during deactivation so that when transferred to the EM-40 Program, only a minimal S & M effort would be required to maintain the building safety envelope. Other than the minimal S & M activities the building will be unoccupied and the exterior doors locked to prevent unauthorized access. The building will be entered only to perform the required S & M until decommissioning activities begin.


Final Deactivation Report on the Radioisotope Production Lab-D, Building 3031, at Oak Ridge National Laboratory, Oak Ridge, Tennessee

Final Deactivation Report on the Radioisotope Production Lab-D, Building 3031, at Oak Ridge National Laboratory, Oak Ridge, Tennessee
Author:
Publisher:
Total Pages: 65
Release: 1997
Genre:
ISBN:

Download Final Deactivation Report on the Radioisotope Production Lab-D, Building 3031, at Oak Ridge National Laboratory, Oak Ridge, Tennessee Book in PDF, ePub and Kindle

The purpose of this report is to document the condition of Bldg. 3031 after completion of deactivation activities as outlined by the Department of Energy Office of Nuclear Materials and Facility Stabilization Program (EM-60) guidance documentation. This report outlines the activities conducted to place the facility in a safe and environmentally sound condition for transfer to the Department of Energy Office of Environmental Restoration (EM-40) Program. This report provides a profile of Bldg. 3031 before and after deactivation activities. Turnover items, such as the Postdeactivation Surveillance & Maintenance Plan, remaining hazardous materials, radiological controls, Safeguards and Security, quality assurance, facility operations, and supporting documentation provided in the Office of Nuclear Materials and Facility Stabilization Program (EM-60) Turnover package, are discussed. Building 3031 will require access to facilitate required surveillance and maintenance activities to maintain the building safety envelope. Building 3031 was stabilized during deactivation so that when transferred to the EM-40 program, only a minimal surveillance and maintenance effort would be required to maintain the building safety envelope. Other than the minimal surveillance and maintenance activities, the building will be unoccupied and the exterior doors locked to prevent unauthorized access. The building will be entered only to perform the required surveillance and maintenance. All materials have been removed from the building and the hot cell, and all utility systems, piping, and alarms have been deactivated.


Final Deactivation Report on the Radioisotope Production Lab-E, Building 3032, at Oak Ridge National Laboratory, Oak Ridge, Tennessee

Final Deactivation Report on the Radioisotope Production Lab-E, Building 3032, at Oak Ridge National Laboratory, Oak Ridge, Tennessee
Author:
Publisher:
Total Pages: 121
Release: 1997
Genre:
ISBN:

Download Final Deactivation Report on the Radioisotope Production Lab-E, Building 3032, at Oak Ridge National Laboratory, Oak Ridge, Tennessee Book in PDF, ePub and Kindle

The purpose of this report is to document the condition of Bldg. 3032, after completion of deactivation activities as outlined by the Department of Energy (DOE) Office of Nuclear Materials and Facility Stabilization Program (EM-60) guidance documentation. This report outlines the activities conducted to place the facility in a safe and environmentally sound condition for transfer to the DOE Office of Environmental Restoration Program (EM-40). This report provides a history and profile of Bldg. 3032 prior to commencing deactivation activities and a profile of the building after completion of deactivation activities. Turnover items, such as the Postdeactivation Surveillance & Maintenance Plan, remaining hazardous materials, radiological controls, Safeguards and Security, quality assurance, facility operations, and supporting documentation provided in the EM-60 turnover package are discussed. Building 3032 will be used as the Health Physics Office for the Isotopes Facilities Deactivation Program area and will require access for these offices and to facilitate required surveillance and maintenance (S & M) activities to maintain the building safety envelope. Bldg. 3032 was stabilized during deactivation so that when transferred to the EM-40 program, only a minimal S & M effort would be required to maintain the building safety envelope. All materials have been removed from the building, and all utility systems, piping, and alarms have been deactivated except electricity and steam needed for the office areas.


Final Deactivation Report on the Radioisotope Production Lab-C, Building 3030, at Oak Ridge National Laboratory, Oak Ridge, Tennessee

Final Deactivation Report on the Radioisotope Production Lab-C, Building 3030, at Oak Ridge National Laboratory, Oak Ridge, Tennessee
Author:
Publisher:
Total Pages: 70
Release: 1997
Genre:
ISBN:

Download Final Deactivation Report on the Radioisotope Production Lab-C, Building 3030, at Oak Ridge National Laboratory, Oak Ridge, Tennessee Book in PDF, ePub and Kindle

The purpose of this report is to document the condition of Bldg. 3030 completion of deactivation activities as outlined by the Department of Energy (DOE) Office of Nuclear Materials and Facility Stabilization Program (EM-60) guidance documentation. This report outlines the activities conducted to place the facility in a safe and environmentally sound condition for transfer to DOE's Office of Environmental Restoration Program (EM-40). This report provides profile of Bldg. 3030 before and after deactivation activities. Turnover items, such as the Postdeactivation Surveillance & Maintenance Plan, remaining hazardous materials, radiological controls, Safeguards and Security, QA, facility operations, and supporting documentation provided in the Office of Nuclear Materials and Facility Stabilization Program (EM-60) Turnover package are discussed. Building 3030 will require access to facilitate required S & M activities to maintain the building safety envelope. Building 3030 was stabilized during deactivation so that when transferred to the EM-40 program, only a minimal S & M effort would be required to maintain the building's safety envelope. Other than the minimal S & M activities, the building will be unoccupied and the exterior doors locked to prevent unauthorized access. The building will be entered only for required S & M. All materials have been removed from the building and the hot cell, and all utility systems, piping, and alarms have been deactivated.


Life Cycle Baseline Summary for ADS 6504IS Isotopes Facilities Deactivation Project at Oak Ridge National Laboratory, Oak Ridge, Tennessee

Life Cycle Baseline Summary for ADS 6504IS Isotopes Facilities Deactivation Project at Oak Ridge National Laboratory, Oak Ridge, Tennessee
Author:
Publisher:
Total Pages: 88
Release: 1995
Genre:
ISBN:

Download Life Cycle Baseline Summary for ADS 6504IS Isotopes Facilities Deactivation Project at Oak Ridge National Laboratory, Oak Ridge, Tennessee Book in PDF, ePub and Kindle

The purpose of the Isotopes Facility Deactivation Project (IFDP) is to place former isotopes production facilities at the Oak Ridge National Laboratory in a safe, stable, and environmentally sound condition; suitable for an extended period of minimum surveillance and maintenance (S & M) and as quickly and economically as possible. This baseline plan establishes the official target schedule for completing the deactivation work and the associated budget required for deactivation and the necessary S & M. Deactivation of the facilities 3026C, 3026D, 3028, 3029, 3038E, 3038M, and 3038AHF, the Center Circle buildings 3047, 3517, and 7025 will continue though Fiscal Year (FY) 1999. The focus of the project in the early years will be on the smaller buildings that require less deactivation and can bring an early return in reducing S & M costs. This baseline plan covers the period from FY1995 throughout FY2000. Deactivation will continue in various facilities through FY1999. A final year of S & M will conclude the project in FY2000. The estimated total cost of the project during this period is $51M.


Final Deactivation Report on the Radioisotope Production Lab-H, Building 3118, at Oak Ridge National Laboratory, Oak Ridge, Tennessee

Final Deactivation Report on the Radioisotope Production Lab-H, Building 3118, at Oak Ridge National Laboratory, Oak Ridge, Tennessee
Author:
Publisher:
Total Pages: 76
Release: 1997
Genre:
ISBN:

Download Final Deactivation Report on the Radioisotope Production Lab-H, Building 3118, at Oak Ridge National Laboratory, Oak Ridge, Tennessee Book in PDF, ePub and Kindle

This report outlines the activities conducted to place the facility in a safe and environmentally sound condition for transfer to the DOE Office of Environmental Restoration Program (EM-40). This report provides a history and profile of Bldg. 3118 prior to and after deactivation. Turnover items (e.g. Surveillance & Maintenance Plant, remaining materials, etc.) are discussed. Building 3118 was stabilized during deactivation so that when transferred to the EM-40 program, only minimal S & M is required (other than that, the building will be unoccupied and the exterior doors locked).